Projects requesting support fro
|
|
DISCRIPTION |
DEADLINES |
|
|
|
|
|
INTIAL
CONTACT Step 1 |
Contact
Provide
the following infor a,
Brief description of your intended research, b,
Date(s) & duration of field season(s), c,
Description of your logistic needs, for exa , i.,
instru ,
ii., any special power require ,
iii., IT/Internet for data transfer, , d,
Obtain a support request for |
|
|
|
|
|
|
LETTER
OF SUPPORT Step 2 |
Contact Dr. Donie
Bret-Harte for science support and letter of support Provide the following
infor a, Co b, Date(s) & duration
of field seasons(s) c, Obtain a letter of
support fro |
Two weeks before funding application deadline |
|
|
|
|
|
Step 3 |
Contact Toolik GIS Office
to begin research site selection process Provide the following
information: a, Requirements of your
research site, for example: , i., vegetation- moist acidic
tundra, shrubs, , , , ii., topographic-
elevation, slope, , , , , iii. , hydrographic-
water proximity, , , , , iv., geographic- Imnavait
watershed, Toolik Lake, Anaktuvuk Burn, , v. , infrastructure-
away from roads, near boardwalks, close to MetStation b, Obtain completed map
and GPS coordinates for proposed research sites |
GIS staff need one month lead time before you anticipate submitting permit application. |
|
|
|
|
|
PRELIMINARY
PERMIT SCOPING WITH BLM Step 4 |
Contact Joyce Voight at
AK BLM Office to begin BLM Permit application process, |
Two months before you plan to submit application. |
|
|
|
|
|
PROJECT
FUNDED Step 5 |
Notify Toolik and BLM project was funded. |
|
|
|
|
|
|
BLM
PERMIT APPLICATION Step 6 |
Contact Joyce Voight at
AK BLM Office to begin BLM Permit process, Provide the following
information: a, Complete description
of your research b, Completed map and GPS
coordinates for proposed research sites c, Submit payment for BLM
permit fee d, Obtain BLM permit
approval NOTE: If you application is not complete, the
review process will not begin. The preferred time to submit applications for
summer field work is January/February. |
Allow at minimum three months for processing. |
|
|
|
|
|
BLM
PERMIT AWARDED |
Permit approved, fees paid to BLM. Submit copy to IAB-Logistics Office. |
|
|
|
|
|
|
START
FIELD WORK |
|
|